| Nature |
Place |
Duration |
Year Started |
Year of Completion |
Client |
Current Status |
| Construction of C & E Type Apartment for
Pakistan Housing Authority at G-11/3, Islamabad
Infrastructure Development Works |
Islamabad |
12 Months |
2010 |
2011 |
Pakistan
Housing
Authority |
On-Going
90% work
Completed and
6 Months Ahead
of Schedule |
| Construction of Parking Plaza at Shahabuddin
Market Adjacent to Empress Market,
Saddar Karachi. |
Karachi |
24 Months |
2009 |
2011 |
City District
Government |
On-Going |
| Construction of C Type Apartment
at G-11/3, Islamabad. |
Islamabad |
24 Months |
2008 |
2009 |
Pakistan
Housing
Authority |
On-Going
Structural and
Plaster work
Completed |
| Construction of E Type Apartment
at G-11/3, Islamabad. |
Islamabad |
24 Months |
2008 |
2010 |
Pakistan Housing Society |
On-Going
Structural and
Plaster work
Completed |